As promised PD started on site yesterday and performed the site scrape. We also have a big security fence and a port a loo in place too.
The footprint of the house actually looks like quite small, but I'm sure it's been measured out properly and it's just a trick of the perspective.
Wednesday, 29 March 2017
Wednesday, 22 March 2017
Start Dates confirmed
PD have confirmed our site start and slab pour dates:
- Site Cut - 28th March 2017
- Slab Pour - 7th April 2017
Saturday, 18 March 2017
Ready to Go
We got moved to construction late last week and we are expecting a site start in the next 7 - 10 days fingers crossed.
So today we needed to do our final site clear in readiness to be handing over to PD.
What a warm/wet summer does for weeds. This was taken about a fortnight before the build should start. Some clearing has started but much more to be done ...
So today we needed to do our final site clear in readiness to be handing over to PD.
What a warm/wet summer does for weeds. This was taken about a fortnight before the build should start. Some clearing has started but much more to be done ...