Timelines
The rough list of events and dates
- September 2016 - Plot bought
- Early October 2016 - Sign sales with Porter Davis to build the Somerville
- 27 October 2016 - 1st World of Style appointment
- 30 October 2016 - 2nd World of Style appointment
- 12 December 2016 - Tender appointment
- 19 December 2016 - Contract appointment
- 28 December 2016 - Power Pit application lodged
- Early March 2017 - Power Pit installed
- 28 March 2017 - Site Scrape
- 15 May 2017 - Frame Start
- 25 May 2017 - Frame Complete
- 29 May 2017 - Gutter and Roof Prep Started
- 1 June 2017 - Roof Tiles On
- 17 June 2017 - Bricks Start
- 23 June 2017 - Insulation In
- 12 July 2017 - Plaster Start
- 26 July 2017 - Bricks Finish
- 28 July 2017 - Scaffolding Down
- 28 July 2017 - Wet areas waterproofed
- 29 July 2017 - Cabinetry delivered
- 9 August 2017 - Painting started
- 18 August 2017 - Painting Complete
- 18 August 2017 Front render started and finished
No comments:
Post a Comment