Timelines

The rough list of events and dates


  • September 2016 - Plot bought
  • Early October 2016 - Sign sales with Porter Davis to build the Somerville
  • 27 October 2016 - 1st World of Style appointment
  • 30 October 2016 - 2nd World of Style appointment
  • 12 December 2016 - Tender appointment
  • 19 December 2016 - Contract appointment
  • 28 December 2016 - Power Pit application lodged
  • Early March 2017 - Power Pit installed
  • 28 March 2017 - Site Scrape
  • 6 April 2017 - Slab Pour
  • 15 May 2017 - Frame Start
  • 25 May 2017 - Frame Complete
  • 29 May 2017 - Gutter and Roof Prep Started
  • 1 June 2017 - Roof Tiles On
  • 17 June 2017 - Bricks Start
  • 23 June 2017 - Insulation In
  • 12 July 2017 - Plaster Start
  • 24 July 2017 - Stairs In
  • 26 July 2017 - Bricks Finish
  • 28 July 2017 - Scaffolding Down
  • 28 July 2017 - Wet areas waterproofed
  • 29 July 2017 - Cabinetry delivered
  • 9 August 2017 - Painting started
  • 18 August 2017 - Painting Complete
  • 18 August 2017 Front render started and finished